Recent / Current Execution Experience

DVC HTLS Conductor Project

Work

HTLS Stringing

Quantity

1.7 CKM

Status

Completed

Reference Date

30 Apr 2025

Project corridor as awarded Completed (reference dated 30 April 2025)
Undertaking

Issued by LS Cable India Pvt. Ltd.

Ref PO LSCI/DVC/24-25/PIPL/001 · 30 Apr 2025

Download PDF

Scope of Work

  • Stringing & installation of HTLS conductor

Client: LS Cable India Private Limited. PO No. LSCI/DVC/24-25/PIPL/001. Stringing & installation of HTLS conductor — 1.7 CKM completed.